Birse Metro Awarded Platform Lengthening Works at Royal Oak Station - 13.4.2010
|
|
Including a design phase, the project consists of a new extension of the island
platform in an easterly direction by 11.8m and the construction of a new 8m long
end ramp. In addition, the existing platform lighting is to be extended to facilitate
the platform lengthening work, whilst the existing track signalling will also
be relocated to accommodate the use of the seventh car.
Interfaces of third party assets include the incorporation of the existing Network
Rail (OLE) overhead line equipment within the footprint; the extended platform
and temporary modification / relocation of existing signalling; and communications
cabling. The electrical installations will be undertaken by Birse Metro’s in
house Electrical Division.